Decommissioning and Demolition Services for Rolls-Royce Corporation
Overview:
KERAMIDA was contracted to provide a variety of services related to the decommissioning and demolition of portions of the Rolls-Royce complex located in Indianapolis, Indiana.
Project Details:
KERAMIDA developed a Pre-Demolition Environmental Work Plan, and our work included:
Inspection of non-structural items
Identification and tagging regulated materials for removal prior to demolition, universal waste
Confirmation that items are sufficiently free of oils to allow transportation to recycler or landfill
Identification and tagging items that cannot be sufficiently inspected or that contained excessive oils
and require additional management before removal, such as low level radioactive waste, exit lighting, smoke detectorsIdentification, tagging and sampling mercury contaminated waste, laboratory drain traps, laboratory benches
Conducted asbestos inspection and developed asbestos abatement plan
Identification of non-liquid PCBs materials such as caulks, paints, glazing coating, and sealants and conducted sampling and analysis
Addressed the regulatory status of the scrap metal as “obsolete scrap metal” per EPA’s guidelines to be managed as a solid waste and exempt from hazardous waste regulations when recycled
Reviewed historic and current operations information; identified areas considered Hazardous Waste Management Units (HWMUs) required to be closed under 40 CFR 262.17(a)(8); developed HWMU closure performance specifications in accordance with state & federal regulations
Confirmation of structural materials to remain in-place after demolition through sampling & analysis; determined if extra cleaning was required
KERAMIDA also performed the following tasks:
Phase I Environmental Site Assessment
Post-Demolition Assessment (including sampling and analysis)
Perimeter air monitoring during work activities
Asbestos abatement oversight final clearance, and final reporting
Hazardous materials abatement oversight, final clearance, final reporting
Related Services:
Companies considering plant closures can rely on KERAMIDA to undertake all services throughout the deactivation, decommissioning, demolition, and redevelopment process, using our innovative and cost-effective phased approach that saves both time and money, and ensures a successful Facility Decommissioning project.